CRCP Repairs – A2 Boughton Bypass Phase 1

A2 Boughton BypassLMS Highways Ltd.

Three weekends of CRCP Carriageway Repairs have come to a close for LMS Highways.

Starting in mid June and running over three consecutive weekends the LMS Highways team have installed over 113m³ of CRCP repairs and 548lm of joint sealing to both the East & Westbound carriageways of the A2, Boughton Bypass.

Read more

08/07/2021/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2021/07/Shift_Photo_51f9f1c4-0de8-4ee7-9143-c24c57008aa6_2021-06-26-04-40-54_f34-scaled.jpg 1271 2560 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2021-07-08 13:20:532024-05-09 09:40:02CRCP Repairs – A2 Boughton Bypass Phase 1
Highway Repairs

CRCP Carriageway Repairs – M60

Carriageway RepairsLMS Highways Ltd.

LMS Highways proves their efficiency and precision in delivering CRCP concrete repairs.

Recently working on behalf of Balvac the LMS Highways team delivered a programme of CRCP repairs to the M60 North and Southbound carriageway. As we work through the list of projects that have been accelerated to be delivered whilst the roads are quieter, this stretch of road had been a nightmare for a long time with high traffic flows, restricted access and some design and build challenges.

Read more

01/04/2021/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2021/05/1615891352369.jpeg 1512 2016 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2021-04-01 12:00:312021-05-27 13:00:05CRCP Carriageway Repairs – M60
Highway Repairs

Concrete Maintenance Project – M53

M53LMS Highways Ltd.

Starting in early February, LMS Highways have been working on behalf of Balvac to deliver a Concrete Maintenance Project located on the M53.

Working between junction 11 – 12 on the M53 LMS Highway were instructed to remove old, damaged sections of concrete carriageway and prepare the subbase in preparation for the road to receive asphalt reinstatement. Along with this, partial depth concrete repairs and further life extension repairs such as thin bond and joint repairs were provided.

Read more

08/03/2021/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2021/03/Shift_Photo_d9dba335-827d-41bd-bafb-058007e07a52_2021-02-20-02-20-08_394.jpg 1434 2448 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2021-03-08 12:00:452021-05-11 14:09:19Concrete Maintenance Project – M53
Highway Repairs

LMS Highways Concrete Bay Replacements

We can’t believe this was three years ago already! Seems only yesterday we were on the A120 delivering rapid concrete bay replacements.

Read more

23/06/2020/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png 0 0 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2020-06-23 15:21:402021-08-05 14:57:49LMS Highways Concrete Bay Replacements
Highway Repairs

M20 Major Concrete Repairs

M20 Major Concrete RepairsLMS Highways Ltd.

During these challenging and uncertain times, one message from the UK Government is clear – Stay at Home, Protect the NHS, Save Lives.

Maintaining a safe and usable highway network is crucial to ensure our key workers can continue travelling to places of work and essential deliveries can be made throughout the country to those in need. To guarantee this remains possible, LMS Highways crews are working across the country providing operationally essential road repairs. Most recently working for A-one+ Area-4 delivering major motorway repairs on the M20 Junction 8 – 9 which included several full depth, rapid concrete bay replacements all whilst complying with the construction leadership council’s guidelines for COVID-19.

Read more

01/04/2020/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2020/04/Shift_Photo_16b1b965-be22-4bf2-afb4-76a004e8e178_2020-03-30-09-34-09_2aa-scaled.jpeg 2560 1920 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2020-04-01 14:49:332021-02-11 16:04:58M20 Major Concrete Repairs
Highway Repairs

Light Aircraft Incident Destroys Section of A40 – LMS Highways Project Team Provide Urgent Repair Services

BBC UK A40BBC UK
Image taken from bbc.co.uk

Back in May a light aircraft came down onto the A40 dual carriageway near Abergavenny, Wales. The occupants escaped moments before a fire took hold of the plane. As a result, the concrete carriageway suffered severe damage and required full bay replacement, joint sealing and new road markings.

At LMS Highways we pride ourselves on delivering package works like these which benefit customers with increased accountability, single point of contact and often providing 10-15% savings.

Read more

24/10/2019/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2019/08/planecrash.jpg 351 624 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2019-10-24 15:02:412021-02-11 16:05:32Light Aircraft Incident Destroys Section of A40 – LMS Highways Project Team Provide Urgent Repair Services
Highway Repairs

UK heatwave doesn’t stop LMS Highways delivering ahead of schedule

The LMS Highways project team have been busy refurbishing sections of an urban concrete road in Kent. Works included new kerbing, concrete bay replacements, white lining and joint sealing which perfectly demonstrates the company’s unique ability to deliver a wide range of services under one point of accountability. The recent run of hot weather has proven challenging but didn’t stop the team from finishing 3 days ahead of schedule.

Read more

30/08/2019/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2024/05/DSC08341-min-scaled.jpg 1704 2560 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2019-08-30 14:40:252024-05-17 13:01:21UK heatwave doesn’t stop LMS Highways delivering ahead of schedule
Highway Repairs

LMS Crack and Joint Repair crew visits AB Port of Southampton

LMS Highways working on behalf of Coupe Line recently visited Associated British Ports, Southampton, to provide Fill & Overband Crack Repair to their damaged port access road.

Before AB Ports could have the excessively damaged access road re-surfaced, any crack deeper than 3mm required Joint Sealing to ensure a successful finish on the new road surface.

Read more

21/08/2019/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2019/07/DSC08340.jpg 3632 5456 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2019-08-21 13:49:042024-05-17 12:59:33LMS Crack and Joint Repair crew visits AB Port of Southampton
Highway Repairs

LMS deliver essential Brexit concrete carriageway repairs

M20 Concrete Bay ReplacementsLMS Highways Ltd

M20 Concrete Carriageway Repairs- LMS provide tailor made and cost-effective solutions

With the UK facing Brexit uncertainty, Highways England identified the M20 as a key strategic corridor and gateway to Europe. They turned to A-One+ and LMS Highways to find a cost effective and timely solution to repair deteriorating sections of the existing concrete carriageway.

Read more

01/07/2019/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2019/06/33fd60b9-ac5c-4a78-9b28-a60c102bd91d-e1561634006169.jpg 947 710 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2019-07-01 09:42:022021-08-05 15:51:45LMS deliver essential Brexit concrete carriageway repairs
Highway Repairs

LMS Civil Solutions team removes 1,200 tonnes of concrete over two nights on the M23

Working recently on the M23 northbound near Gatwick Airport. LMS Highways’ concrete bay removal process was put to the test.

The scheme was completed over 4 weekends with partial and full overnight closures resulting in minimised disruption.

Our video shows how the team removed a total of 1,200 tonnes (400 linear metres of concrete) over one weekend.

Read more

17/05/2018/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2015/10/civils_concrete_bay_replacement_dereham_08.jpg 682 1024 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2018-05-17 12:00:322021-02-11 16:06:51LMS Civil Solutions team removes 1,200 tonnes of concrete over two nights on the M23
Page 2 of 3123

Categories

  • Frequently Asked Questions
  • Social Values
  • Highway Repairs
  • General Civils & Associated Repairs
  • News Items

Case Studies

  • A35 Flange Beam Replacement07/07/2026 -
  • LMS Highways Ltd
    A50 Flange Beam Replacement14/01/2026 -
  • A50LMS Highways
    A50 Multi-phase Project06/11/2025 -

LMS Highways Ltd.

Address:
LMS Highways
Cockington Court, Cockington Village,
Torquay, Devon, UK
TQ2 6XA

Contact:
contact@lmshighways.co.uk
01626 331771

Office Opening Hours:
Mon – Fri: 09:00 – 17:00

Terms & Conditions                            Privacy Policy

Terms of Purchase Order                    Brochure

 

Social Values

Proud supporters of

Copyright © LMS Highways Ltd. All Rights Reserved. Registered Company Number: 01098038; VAT Number: 232754709
  • Link to LinkedIn
  • Link to Facebook
  • Link to Youtube
  • Link to X
Scroll to top Scroll to top Scroll to top