LMS Civil Solutions team removes 1,200 tonnes of concrete over two nights on the M23

Working recently on the M23 northbound near Gatwick Airport. LMS Highways’ concrete bay removal process was put to the test.

The scheme was completed over 4 weekends with partial and full overnight closures resulting in minimised disruption.

Our video shows how the team removed a total of 1,200 tonnes (400 linear metres of concrete) over one weekend.

Read more

17/05/2018/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2015/10/civils_concrete_bay_replacement_dereham_08.jpg 682 1024 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2018-05-17 12:00:322021-02-11 16:06:51LMS Civil Solutions team removes 1,200 tonnes of concrete over two nights on the M23
Highway Repairs

LMS Civil Solutions Urban Concrete Bay Replacement

Kent - Concrete Bay ReplacementLMS Highways Ltd.

Applying our motorway and trunk road concrete bay replacement process into an urban environment.

The LMS team have been working for a main contractor customer in Kent, with the aim of applying their highly successful concrete bay replacement service into a residential and urban setting.

Read more

10/01/2018/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2015/10/Residential-bay-removal-1.jpg 2120 4032 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2018-01-10 12:00:232024-05-14 14:05:01LMS Civil Solutions Urban Concrete Bay Replacement
Highway Repairs

18 months of success for the LMS Civil Solutions team

Concrete RepairsLMS Highways Ltd.

Just under 2 years ago, the Directors of LMS Highways started to investigate wider opportunities available as a natural extension of their popular and respected highway repair solutions.

Six months later, the company launched LMS Civil Solutions. Enlisting the services of industry-veteran and self-described ‘concrete-nerd’ Paul Burton, ‘Nobby’.

Since the launch at the beginning of 2016, the company has undertaken work across several diverse projects, some of these being standalone civils projects and others were a natural partnership between LMS Highways and LMS Civil Solutions offering ‘kerb to kerb’ highways packages. All having great customer satisfaction in common.

Read more

06/11/2017/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2018/08/IMG_1016.jpg 2448 3264 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2017-11-06 12:00:312021-08-06 09:05:4418 months of success for the LMS Civil Solutions team
Highway Repairs

Kerb to Kerb highway repairs on A120 trunk road brings cost savings and accountability

LMS Highways and LMS Civil Solutions combined their highly experienced teams to bring a joined-up highway repairs service on the A120 in Essex in February.

Starting with LMS Civil Solution’s highly-respected concrete bay replacement system to replace faulty slabs, the work took place over three nights.

Two slabs were extracted and replaced each night using our highly effective vacuum-lift system and a rapid-cure concrete solution was used allowing the road to be re-opened safely after each shift.
Read more

01/03/2017/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2015/10/Joint-Repair-M180.jpg 3024 4032 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2017-03-01 12:00:062021-02-11 16:07:18Kerb to Kerb highway repairs on A120 trunk road brings cost savings and accountability
General Civils & Associated Repairs

LMS Civil Solutions Salt Barn – First Phase Completed

LMS Highways Ltd.

This work, is a typical example of how LMS Civil Solutions with their knowledge and experience are able to excel and impress in very difficult conditions.

The initial phase of constructing the ring beam and pouring the concrete would normally be allocated 8 weeks for completion. However, for various reasons prior to LMS’s engagement in the project, the team were left with just 3 weeks to complete the initial phase to stay within the challenging programme.

In order to achieve this, LMS’s Paul Burton has been working closely with all and has been playing an important role in the overall project management. He told us:

“The difficulties with the reduced time frame meant that we’ve not only had to work in a reduced operating space along with the other team who are busy assembling the structure, but we’ve also had to ensure that we’re not causing any disruption to the 24/7 operations of this busy network hub. The very hot weather towards the end of this phase has created additional challenges”.

Read more

10/08/2016/by Harriet Drew
https://lmshighways.co.uk/wp-content/uploads/2014/05/lms-civil-solutions-salt-barn-01.jpg 1936 2592 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2016-08-10 15:14:582024-05-09 14:16:38LMS Civil Solutions Salt Barn – First Phase Completed
Page 6 of 6«‹456

Categories

  • Frequently Asked Questions
  • Social Values
  • Highway Repairs
  • General Civils & Associated Repairs
  • News Items

Case Studies

  • A35 Flange Beam Replacement07/07/2026 -
  • LMS Highways Ltd
    A50 Flange Beam Replacement14/01/2026 -
  • A50LMS Highways
    A50 Multi-phase Project06/11/2025 -

LMS Highways Ltd.

Address:
LMS Highways
Cockington Court, Cockington Village,
Torquay, Devon, UK
TQ2 6XA

Contact:
contact@lmshighways.co.uk
01626 331771

Office Opening Hours:
Mon – Fri: 09:00 – 17:00

Copyright © LMS Highways Ltd. All Rights Reserved. Registered Company Number: 01098038; VAT Number: 232754709
  • Link to LinkedIn
  • Link to Facebook
  • Link to Youtube
  • Link to X
Scroll to top Scroll to top Scroll to top