CRCP Repairs – A2 Boughton Bypass Phase 1

A2 Boughton BypassLMS Highways Ltd.

Three weekends of CRCP Carriageway Repairs have come to a close for LMS Highways.

Starting in mid June and running over three consecutive weekends the LMS Highways team have installed over 113m³ of CRCP repairs and 548lm of joint sealing to both the East & Westbound carriageways of the A2, Boughton Bypass.

All sections of damaged carriageway were removed using our bespoke lifting bucket, which compared to traditional equipment is capable of lifting and removing large slabs of concrete without the need for breaking down in advance.
Concrete Repairs
Concrete Repairs
Concrete Repairs
Concrete Repairs
Concrete Repairs
Concrete Repairs
Crack & Joint Repairs
Crack & Joint Repairs
The bays were then prepped with rebar; continuously reinforced concrete pavement is constructed with steel reinforcing bars placed within the concrete, continuously along the entire length of the pavement. The result is a continuous, smooth-riding surface capable of withstanding the heaviest traffic loads and the most adverse weather conditions. To extend the service life of the new concrete bays and prevent water ingress, the team then install joint sealing around the bays.
  • 9 Shifts taking place over three consecutive weekends
  • Over 113 m³ of concrete poured
  • Approximately 548 linear metres of joint sealing
  • Over 12 m³ of thin bond repairs

The LMS Team

With decades of experience, we pride ourselves on our quality of service and ability to meet our customers’ requirements.

If you have an enquiry relating to Concrete Repairs or Project Works then please give us a call on 01626 331771.

08/07/2021/by Harriet Drew
Share this entry
  • Share on Facebook
  • Share on X
  • Share on LinkedIn
  • Share by Mail
https://lmshighways.co.uk/wp-content/uploads/2021/07/Shift_Photo_51f9f1c4-0de8-4ee7-9143-c24c57008aa6_2021-06-26-04-40-54_f34-scaled.jpg 1271 2560 Harriet Drew https://lmshighways.co.uk/wp-content/uploads/2019/04/lms-inline-transparency.png Harriet Drew2021-07-08 13:20:532024-05-09 09:40:02CRCP Repairs – A2 Boughton Bypass Phase 1

Categories

  • Frequently Asked Questions
  • Social Values
  • Highway Repairs
  • General Civils & Associated Repairs
  • News Items

Case Studies

  • A35 Flange Beam Replacement07/07/2026 -
  • LMS Highways Ltd
    A50 Flange Beam Replacement14/01/2026 -
  • A50LMS Highways
    A50 Multi-phase Project06/11/2025 -

LMS Highways Ltd.

Address:
LMS Highways
Cockington Court, Cockington Village,
Torquay, Devon, UK
TQ2 6XA

Contact:
contact@lmshighways.co.uk
01626 331771

Office Opening Hours:
Mon – Fri: 09:00 – 17:00

Terms & Conditions                            Privacy Policy

Terms of Purchase Order                    Brochure

 

Social Values

Proud supporters of

Copyright © LMS Highways Ltd. All Rights Reserved. Registered Company Number: 01098038; VAT Number: 232754709
  • Link to LinkedIn
  • Link to Facebook
  • Link to Youtube
  • Link to X
Link to: #03. You Ask, We Answer – Can you repair CRCP? Link to: #03. You Ask, We Answer – Can you repair CRCP? #03. You Ask, We Answer – Can you repair CRCP? Link to: Henwood Industrial Estate Repairs Link to: Henwood Industrial Estate Repairs Henwood Industrial Estate RepairsLMS Highways Ltd.Henwood Industrial Estate Repairs
Scroll to top Scroll to top Scroll to top